Strategy,
Finance & City Regeneration Committee
|
Agenda Item
26
|
Subject:
General Fund
Budget Planning & Resources Update 2024/25
Date of
meeting: 13 July 2023
Report
of:
Chief Finance Officer
Contact
Officers: Name: Nigel Manvell, James
Hengeveld
Tel: 01273 293104, 01273 291242
Email: Nigel.Manvell@brighton-hove.gov.uk
James.Hengeveld@brighton-hove.gov.uk
FOR
GENERAL RELEASE
1
PURPOSE OF REPORT AND POLICY CONTEXT:
1.1
This report provides a budget planning and resource update in
preparation for the start of the 2024/25 annual budget setting and
medium term planning process. The previous three years have been
highly unusual, including two years affected by the pandemic
followed by a year of exceptionally high inflation driven by global
events. While the pandemic years were generally supported by
significant government funding, the exceptional inflationary
pressures experienced last year were supported by an increase in
Spending Power of just 3% compared to CPI that topped out at 11.1%
in October 2022, with no further government funding support
forthcoming during the year.
1.2
The funding settlement for 2023/24 was improved by the
government’s decision to revert Social Care Reform funding to
core funding and to delay the reforms, which provided an 8.9%
increase in Spending Power. However, this did not address the
funding shortfall in 2022/23 and has therefore put many councils in
financial difficulty with widespread overspending evident,
resulting in unplanned calls on reserves to manage the 2022/23
position. This will have also left the majority of authorities with
an underlying pressure being carried into 2023/24.
1.3
This is supported by findings from the annual survey of the
Association of Directors of Adult Social Services (ADASS) which
found that 72% of authorities used reserves to balance their
2022/23 budget – almost double the 37% who did in 2021/22.
This is a significant indicator and a clear sign that the
additional costs driven by high pay, energy and food inflation
severely impacted social care provision, primarily through the
increased commissioning costs of in-house, independent and private
sector home care and residential care costs.
1.4
Following on from over a decade of government grant reductions, the
financial challenges posed by the pandemic, and now a high
inflationary environment, it is not surprising that local
government, nationally, is in an unprecedented financial situation.
The financial sustainability of many authorities is being called
into question, including this authority where the external auditor
has highlighted financial sustainability as a significant weakness
in their Annual Report 2021-22, particularly given the
authority’s relatively low level of allocated and unallocated
reserves and balances.
1.5
There is now a potentially serious situation developing whereby a
range of financial impacts are all combining to negatively impact
on financial sustainability with very few elements moving in a
favourable direction. These include:
·
Continuing high inflation leading to higher nationally negotiated
pay awards, high contractual and commissioning costs, particularly
for PFI’s and Social Care Providers, and high operational
costs, e.g. energy and transport;
·
An associated cost of living crisis driven by inflation and high
interest rates which directly impacts on private sector rental
costs leading to higher rates of homelessness and higher costs of
leasing Temporary Accommodation together with increased service
demands across adult and children’s social care and an
increased cost of Council Tax Reduction due to increasing claimant
numbers;
·
A challenging economic environment that is very clearly impacting
on visitor spending power and other economic activity, resulting in
suppressed cultural service, parking, planning and many other
incomes as well as pressures on commercial rental incomes;
·
Severe challenges in maintaining Council Tax and Business Rate
collection performance due to the increasing number of people in
financial difficulty and an increase in business insolvencies;
·
A post-pandemic downturn across all labour markets resulting in
high recruitment and retention costs, most notably across Drivers,
Children’s Social Care and Legal Services but generally
across almost all professional groups;
·
Increased costs of capital investment, particularly due to high
construction inflation, resulting in higher Minimum Revenue
Provision (MRP) costs and an increased cost of borrowing;
·
Increasing financial pressures across schools which has resulted in
the General Fund needing to make provision for deficits for schools
transferring to Academies, including Moulescoomb and Homewood
College. However, there are now substantial deficits growing across
many schools that could ultimately impact General Fund resources if
not managed or resolved.
1.6
Although the government announced a high level, two-year spending
review last year, this does not provide local authorities with
reliable information on which to set budgets. Once again, the
planning process for 2024/25 will therefore require key judgements
about likely levels of government funding support, which are not
normally confirmed until autumn/winter. However, other factors are
also difficult to assess, particularly over the medium term
planning period (4 years), and therefore judgements will need to be
made, for example, regarding how long higher inflation and the cost
of living crisis will persist, and the time period for full
economic and visitor recovery over which the council itself may
have some influence through its regeneration, sustainable transport
and other relevant policies.
1.7
Developing estimates in a highly uncertain environment and without
government funding certainty is clearly an unenviable position and
carries with it very high risks for developing a balanced, robust
and sustainable budget. Being too optimistic may impact on
financial sustainability in the short to medium-term if the
situation turns out to be significantly worse, and, conversely,
being too pessimistic could result in unnecessary or damaging cuts
to essential services being considered.
1.8
As in previous years, officers have therefore developed estimates
based on current data, analysis of trends for demand-led services
and consideration of government (OBR) economic data and forecasts.
A balanced view is taken and evidence shows that in the last few
years, and last year in particular, that estimates have not been
over-prudent given that costs and demands have outstripped
estimates and assumptions due to a worsening economic situation. To
derive the potential budget shortfall (gap), estimates of costs
(inflationary and demographic), government funding, fees &
charges incomes, and taxation revenues are drawn up and are
provided below.
1.9
Although the council’s only unallocated reserve is its
Working Balance, it can manage a level of financial risk by either
borrowing from its earmarked reserves or by utilising its Working
Balance in the short term with replenishment over a period of time.
However, the council’s reserves and balances are well below
the average for unitary and upper tier local authorities and it has
already borrowed £5.7 million from its reserves to manage the
impact of the pandemic to date, which could take up to 10 years to
repay. The Provisional Outturn report for 2022/23 showed that the
council will need to use £3.376 million from its Working
Balance to address the overspend incurred with plans to replenish
this over 3 years. This will require £1.125 million resources
to be identified for the next 3 years, adding to future budget gaps
and the financial pressure.
1.10 Entering into a
new term of Administration and in light of the External
Auditor’s recommendations regarding improving financial
sustainability, there is an opportunity to build towards a longer
term view and develop proposals to address not only the next
financial year, as legally required, but to aim for financial
sustainability over the Medium Term 4-year planning period. This
will be important for a number of reasons including:
·
Demonstrating that the council is setting its annual budgets in the
context of understanding its longer term financial
sustainability;
·
Demonstrating that any use of reserves or balances in the
short-term to support the budget is financially sustainable (i.e.
repayable) in the medium term;
·
Ensuring that delivery of the Council’s Corporate Plan
priorities and associated service planning is aligned with
medium-term financial planning and sustainability, and;
·
Ensuring that any budget shortfalls (gaps) in future years are
identified early to enable longer term programmes of change to be
identified and instigated as soon as possible in order to generate
necessary savings, efficiencies or income.
1.11 The medium term
planning process will consider both the service and financial
strategies required to maintain financial sustainability over the
period while ensuring that core statutory services can be funded
and aiming to support the council’s corporate priorities as
far as possible.
2
RECOMMENDATIONS:
The Strategy, Finance & City
Regeneration Committee is recommended to:
2.1
Note the potential funding and net expenditure projections for
2024/25.
2.2
Note the Medium Term financial projections for 2024/25 to 2027/28
and the predicted budget gaps over the period.
2.3
Note the proposed budget development approach and that officers
will use this to develop 4-year medium-term service and financial
plans and proposals for Budget Council consideration, including
specific budget proposals to manage the identified budget shortfall
in 2024/25.
3
MEDIUM TERM SERVICE & FINANCIAL PLANNING
i)
Single-year financial settlements: Central government
announced a high level, two-year Autumn Statement in 2022 but
followed this up with a short-term, one-year Local Government
Financial Settlement for 2023/24 (the fifth in a row) with no
certainty over funding for 2024/25 and beyond.
ii)
New bidding processes: Significantly, there are also an
increasing number of funding streams, both capital and revenue,
that are now subject to national bidding processes, giving even
less certainty over funding. Most notably for this council, funding
for homelessness and rough sleeping, arts and cultural services,
and sustainable transport are subject to numerous bidding rounds
and significant funding also comes through the NHS but is subject
to annual negotiations. In addition, these processes often transfer
all risk of cost over-runs to the local authority which, in a high
inflationary environment, becomes a significant risk factor.
iii)
Short-term funding: Many of the council’s funding
streams are now temporary or time-limited including important
funding such as the Household Support Fund, some Homelessness
funding, New Homes Bonus, and NHS hospital discharge and mental
health funding;
iv)
Financial reforms: Social Care funding reforms were put on
hold due to concerns raised by the LGA and others about the
potential cost of the reforms. Other potential financial reforms,
including the Fair Funding Review and Business Rates changes, also
appear unlikely to be revisited before the next General Election.
In lieu of these reforms, the government has transferred some
Revenue Support Grant (RSG) to a new temporary ‘Services
Grant’ which is adjusted by government each year for varying
reasons. For example, in 2023/24 it was top-sliced to provide a
minimum settlement increase of 3% for all authorities (which was
not applicable to BHCC) and to fund the CPI increase in Revenue
Support Grant (RSG) thereby resulting in no net gain to the
council.
All of this contributes to financial
uncertainty and makes financial planning very challenging and
perilous at a time when local authority budgets are under
unprecedented pressure.
3.2
Ideally, the budget setting process should therefore allow some
flexibility to manage any adverse fluctuations in the level of
estimated costs, resources or funding. This necessarily requires a
prudent approach in order to:
(i)
avoid exhausting the authority’s reserves and balances
(one-off resources);
(ii)
manage risks effectively and maintain financial resilience and
sustainability over the medium term.
However, setting aside risk reserves or
planning to increase contributions to reserves is very challenging
when faced with substantial annual budget gaps.
3.3
At this early stage of the budget setting process, this report
includes an indicative assessment of the financial pressures facing
priority services in terms of increases in costs, and demographic
growth in demands, particularly in relation to
‘demand-led’ services for vulnerable adults, families
and children such as social care and homelessness. Alongside
government grant reductions, limitations on the allowable level of
council tax increases, and inflationary pressures, these demand-led
cost pressures have been the main driver of the substantial
‘budget gaps’ that the council has been experiencing
over the last decade or so. The impact of high inflation, even if
it begins to fall this year, will further exacerbate pressures in
2024/25, and possibly beyond, depending on the effectiveness of
monetary policy and global economic factors.
·
Notification to and involvement of the Department of Levelling Up,
Housing & Communities (DLUHC) where potential financial
difficulties have reached a critical point and a council is unable
to balance its budget. This can result in a statutory Section 114
report being issued by the Chief Finance Officer (CFO). Such a
report is made to full Council and provides 21 days for the Council
to respond with measures to balance the budget.
·
Public Interest reports being issued by External Auditors where
they believe the authority is not acting or is failing to act
appropriately regarding financial matters.
·
Appointment of independent financial reviewers, usually where a
local authority has identified the need to request a
‘capitalisation direction’ from government whereby it
either needs to sell capital assets and use capital receipts, or
utilise borrowing to fund revenue expenditure in the short term to
keep afloat.
·
In severe cases, appointment of Commissioners to run the council or
parts of the council on behalf of the Secretary of State, for
example, Thurrock Council and Liverpool City Council.
·
In the severest case, Northamptonshire, direct intervention by
government resulted in the dissolution of the authority and
creation of two new unitary authorities from April 2021.
3.5
In their annual reviews, external auditors are therefore
increasingly concerned with local authorities’ arrangements
for securing value for money which includes demonstrating financial
resilience and sustainability and providing evidence of effective
medium term planning. The external auditor’s Annual Report
2021-22 for this authority identified financial sustainability as a
‘significant weakness’ and made a Key Recommendation to
the council to take steps to improve its financial sustainability
and resilience (Audit & Standards Committee, Item 38, 24
January 2023).
Reserves & Balances
3.6
The council’s available reserves and balances are an
important indicator of the council’s financial resilience and
ability to manage unexpected financial impacts. Available reserves
and balances are cash-backed and are held for a wide range of
commitments in the short to long term. This excludes balances held
by the Housing Revenue Account and Schools which are not available
to the General Fund. It also excludes capital reserves which cannot
normally be used for revenue purposes. Levels are currently as
follows:
·
Working Balance £6m – this is a permanent risk
reserve and therefore any use must be accompanied by a plan for
replenishment. Approximately £3m was drawn down to manage the
2022/23 outturn overspend which will need to be repaid over 3 years
to restore the Working Balance to the recommended level of
£9m which represents approximately 4% of the net General Fund
budget. Holding working balances of between 4% and 5% is considered
to be good practice for local authorities;
·
Earmarked Reserves £31m – earmarked reserves are
held in lieu of an approved scheme or expense or an identified
liability and will often span more than one financial year. Many
are held against contractual commitments (e.g. PFI contracts) while
others are held for regeneration projects and are linked to match
funding from the Local Enterprise Partnership or other government
funds. Many will be utilised in the short term, including revenue
‘carry forward’ items, but longer-term earmarked
reserves can be ‘internally borrowed’ from provided
they are replenished in time for when they are required to meet
their intended purpose. Using reserves to defer decisions or to
balance the revenue budget is not sustainable and therefore should
be an exceptional practice only, particularly as reserves are
generally reducing year-on-year and the authority has not been in a
position to improve its reserve position for many years.
3.7
A full list of the council’s reserves and balances as at 31
March 2023 is provided at Appendix 9 of the Targeted Budget
Management (TBM) Provisional Outturn report to the 22 June meeting
of the Strategy, Finance & City Regeneration Committee.
Budget Planning Estimates
Addressing Budget Shortfalls (Gaps)
3.10 The difference
between the estimated costs of services, net of fees, charges and
rents, and the estimated resources available from taxation and
government grant funding determines whether or not there will be a
predicted budget shortfall/gap each year. In common with many
councils, this council has experienced more significant annual
budget gaps since 2010/11 as the demand for services has
substantially increased while government grant funding was
substantially reduced under government ‘deficit
reduction’ policies. While there has been limited redress in
the last few years in terms of increased social care funding and
allowable Adult Social Care Council Tax precepts, which increase
the burden of funding on local taxpayers, the resulting loss of
funding is over £100 million in real terms from 2010/11 to
2023/24.
3.11 A budget gap can
be closed by identifying cost savings and efficiencies, generating
increased income or funding, developing cost avoidance strategies
(e.g. preventative or demand management strategies), or by cutting
or reducing services provided that statutory minimum requirements
can still be met. In summary, the broad options and/or
possibilities for closing any projected budget gaps are therefore
as follows:
(i)
Government may provide a better Local Government Financial
Settlement than currently known or assumed;
(ii)
The council could elect to increase Council Tax above the current
statutory ‘excessive council tax increase threshold’
(i.e. above 2.99%). For example, with inflation currently at around
8.7%, an inflationary council tax increase at this level would
potentially raise an additional £9.9m. However, under current
regulations this would require a local referendum to be held with a
successful outcome. This of itself creates a cost of approximately
£0.400m to hold a referendum and requires identification of
one-off resources to mitigate the delay in implementing proposals
while the outcome is awaited. In the case of a Council Tax
Referendum, it is therefore a legal requirement to have a
‘substitute budget’ should a referendum not be
successful;
(iii)
Partners could provide increased funding for joint operations e.g.
NHS funding toward social care costs. For example, last year NHS
Sussex provided significant hospital discharge funding and agreed
increased funding for Section 117 Mental Health caseloads, which is
again assumed for 2024/25. There may be further opportunities for
shared funding or joint investment through the Integrated Care
System (ICS) to improve longer term care costs but plans are still
at early stages of development. Other partners are small by
comparison;
(iv)
There may be improvements in the projected levels of cost, income
and/or demographic pressures as the council progresses through the
budget process. Estimates will be revisited from time-to-time but
particularly at month 9 (December) ahead of producing the budget
proposals for Budget Council in February 2024. A key activity is
therefore for services to manage down costs and demands in-year
because this not only reduces in-year pressures but addresses
underlying pressures that are the principal cause of budget gaps in
future years;
(v)
Development of medium term service and financial plans by major
service directorates that include identification of potential
savings, efficiencies and cost management measures to either reduce
costs in non-priority areas, manage down pressures in demand-led
areas (e.g. through prevention, commissioning and intervention
strategies), generate greater incomes from fees, charges or
property rents, or develop strategies to attract alternative
funding. These may be multi-year proposals which may then enable
the council to ‘financially smooth’ out budget gaps
over a 4-year medium term period, for example, where savings and
cost reductions steadily increase over the period.
3.12 Options (i) to
(iii) above carry a high level of uncertainty or risk and therefore
the authority will normally need to focus on in-year cost and
demand management to reduce current and forward estimates as
described in (iv) above and develop budget strategies and savings
proposals as described in (v) above.
4-Year Medium Term Financial Planning
3.13 The financial
challenges for this and many authorities, particularly unitaries
with their full range of services, are growing in the current
economic and inflationary environment. While addressing budget
challenges on an annual basis is a statutory requirement in order
to set a legally balanced budget and set a Council Tax, best
practice and the current financial climate would advocate that
longer term planning is also essential to ensure that more
fundamental changes to services, or initiatives to generate income
or funding, are considered now and programmed over a minimum 4-year
planning period. This will help to inform future year estimates and
aid the authority in progressing towards greater financial
resilience and sustainability. It will also help to inform the
capacity and investment needed to achieve change and ongoing
sustainability.
3.14 Developing plans
to cover a longer time frame increases the complexity of the budget
process but could support a more focused and deliverable Medium
Term Financial Strategy (MTFS) and should enable better alignment
of the budget with Corporate Plan priorities over the period.
Setting budgets on a 1-year horizon is likely to be less strategic
and can lead to so-called ‘salami slicing’ where
incremental cuts or cash limits are applied to services each year
that ultimately result in services reaching a tipping point after a
number of budget rounds. Unfortunately, five years of single-year
Local Government Financial Settlements has not supported a longer
term approach.
Components of a
Medium Term Budget Setting Process
·
Review of Capital Programme Deliverability &
Affordability
The council’s
capital programme in recent years has become very large and
fragmented, exceeding £200m per annum. There has also been a
record of very substantial slippage and reprofiling (delays),
indicating that capital investment plans are not realistic or
deliverable within the originally profiled timeframes due to
recruitment, contracting and capacity issues across all sectors.
This was commented on by the External Auditor in their Annual
Report 2021-22, leading to a recommendation to the council to
review and evaluate how it sets its capital programme. The 2024/25
budget process is therefore an opportunity to address these
concerns, fully review the programme and its affordability in the
context of revenue budget pressures, and its alignment with council
priorities. A full and detailed review of existing schemes and
future requirements will therefore be undertaken to inform the
Capital Strategy for 2024/25 and beyond.
·
Capital Financing Review
Linked to the
Capital Programme review above, the associated Capital Financing
budget will also be reviewed. The current capital investment plans
will see very substantial capital financing costs start to flow
from 2024/25 in the form of Minimum Revenue Provision for schemes
supported by borrowing. Therefore, curtailment or deferral of
schemes would not only reduce capital financing costs but would
increase cash balances and therefore revenue investment income.
This is likely to be a key area where substantial savings could be
made without impacting directly on front line service
delivery.
·
Develop and Launch MTFS Workstreams
There are many
potential options that can be explored to improve longer term
financial sustainability. Everything from investing in prevention
to reduce longer term care costs to developing new income sources.
However, these can take significant capacity and investment to
bring to fruition and therefore need to be properly assessed and
evaluated before embarking on a whole host of initiatives with
questionable returns on investment.
·
Develop a Fees & Charges Strategy
Many fees &
charges are regulated and in general fees & charges are set to
recover costs and overheads of the service provided. However, in
some areas the council has more discretion. There are still many
areas where the council does not charge but could legally do so. A
key concern with fees & charges is the equality impact and
impacts on those with low incomes. This can be managed by designing
the fee or charge to accommodate such impacts, for example,
introducing means tests. Many councils have become increasingly
reliant on fees & charges to protect service provision due to
the limitations on Council Tax increases and reduced government
grant funding. Approximately one third of the council’s
General Fund council services are now funded by fees &
charges.
·
Apply Cash Limit or Efficiency Targets
Continually
improving efficiency is good business practice for any
organisation. This can be achieved through continually reviewing
and improving processes (i.e. service redesign), using IT and
digital technologies to automate workflows and services, and
effective procurement and commissioning strategies to utilise the
council’s purchasing power to shape local provision or secure
more competitive terms. To recognise this, some expenditure
categories, e.g. supplies and services, can be cash limited (i.e.
provided with a lower or no inflationary budget uplift or even
reduced) or services can be targeted with generic efficiency
targets (e.g. 1% or 2% reductions) to ensure that all areas of the
council strive for improved value for money. These opportunities
will be a key area to explore in the forthcoming budget
process.
·
Identify Invest-to-Save (Modernisation) Opportunities
Modernisation
funding is discussed later in the report but is now becoming
problematic. The Modernisation Fund was previously supported by the
government’s ‘capital receipt flexibilities’
enabling capital receipts to be used to fund revenue expenditure
provided such expenditure supported improved value for money
and future revenue savings. However, not only do these
flexibilities end in 2025 but, more importantly, the demand on
capital receipts across a range of objectives is such that they are
no longer significant enough to support the necessary investment.
Future invest-to-save or modernisation activities will therefore
need to either:
-
Demonstrate a
clear return on investment over a reasonable time period (max 5
years) which can then be supported by internally borrowing from
reserves with subsequent repayment (subject to availability of
reserves);
-
Alternatively,
investment requirements can be netted off against savings proposals
meaning that the saving in the first year or two is reduced and
then increases to its full extent in later years;
-
If
any element of the invest-to-save proposal is of a capital nature,
borrowing could be considered, provided that a return on investment
can be evidenced in the business case.
·
Explore Fundraising Opportunities
The council has
been successful over many years in bidding for additional revenue
and capital funding including Heritage Lottery funds, Arts Council
Funds, Homelessness and Rough Sleeping (RSI) funding, Levelling Up
funding, Family Hub funding, Department for Transport funding (e.g.
the substantial Bus Partnership bid), Coast to Capital Local
Enterprise Partnership growth funding, and so on. However, there
may be other opportunities available to the council to attract
funding or even to explore changing the funder of some services.
This may require some ‘pump priming’ resources to
research and explore options.
·
Utilise ‘Budget Categorisation’ to inform budget
decisions
Officers have
undertaken a Budget Categorisation exercise to define the different
types of services and budgets across the council and the role that
they play. For example, many services are required to meet
statutory duties and responsibilities such as Adult Social Care,
while others are not statutory but provide essential services such
as Street Lighting, while other services can generate income that
help the authority to mitigate costs and overheads. Six broad
categories have been identified as follows:
Budget Category
|
Approximate % of Spend
|
Meaning / Example
|
Statutory
|
91.3%
|
Unavoidable statutory duty or service requirement / e.g. Adult and
Children’s Social Care
|
Business Critical
|
12.6%
|
Non-statutory but without these services the council could not
function / e.g. Operational Buildings, IT infrastructure and
networking
|
Income
Generating
|
-13.4%
|
Services that generate significant incomes which, if withdrawn,
would create a budget pressure or loss / e.g. Commercial Property
Rents
|
Business Important
|
3.0%
|
Non-statutory but without these services many legal, financial and
service risks would increase, the council would be unlikely to
function as efficiently or effectively, and/or overall costs are
likely to increase / e.g. Support Service functions such as
the Procurement Service
|
Policy
Priority
|
6.0%
|
These
are non-statutory, discretionary services that meet current
Corporate Plan policy priorities / e.g. Welfare Support or
non-statutory Children’s Services
|
Discretionary
|
0.4%
|
Non-statutory, discretionary services that the council has elected
to or has historically provided or commissioned / e.g. Early Years
Nurseries
|
This exercise will
be updated for 2023/24 budgets and changes in category. The
exercise does not of itself inform where savings or cost reductions
are possible but it does provide an alternative way to look at
where money is spent and may help to inform the budget setting
process, particularly where difficult choices may need to be made
to balance the budget. It is clear from the above that even though
a service may be designated as statutory, because these services
represent over 90% of spend they cannot be exempted from exploring
savings and efficiencies. In addition, this exercise does not
consider what the statutory minimum level of service should be for
statutory services as this is often not defined by statute and
cannot be determined.
·
VFM Reviews
The council has a
Best Value duty under the LG Act 1999 requiring it to ‘make
arrangements to secure continuous improvement in the way in which
its functions are exercised, having regard to a combination of
economy, efficiency and effectiveness.’ This is generally
referred to as improving Value for Money (VFM). There are many ways
to test and assure the value for money of services provided by the
council including:
-
Comparing the
cost and quality of services with similar authorities or service
providers;
-
Comparing the
cost of services per capita of the relevant population groups or
service groups e.g. cost of Children’s Services per 1,000
children aged 0 to 24 in the local authority area;
-
Using
external, independent peer challenge to help identify improvements
e.g. LGA peer reviews;
-
Utilising best
practice research to compare services provided by the
authority;
-
Engaging expert
consultancy to help identify and design specific services or
interventions to help improve VFM;
-
Comparing the
cost and quality of in-house provision versus contracted or
outsourced provision (so-called ‘make or buy’
reviews).
·
Utilise Budget Prioritisation to inform budget
decisions
The council
provides a very wide range of services but not all have the same
level of priority and may, for example, offer a greater or lesser
contribution to meeting corporate priorities and statutory duties.
It is therefore possible to develop a set of criteria against which
to assess both services and any potential saving proposals,
including service cuts or reductions. Any number of criteria could
be developed and can be weighted according to relative importance.
This cannot be a precise exercise and will clearly involve a level
of subjectivity but, similar to budget categorisation above, it can
provide an alternative way of looking at the relative importance of
all the services the council provides, of which there are hundreds,
and may be useful to inform, or at least affirm, budget
decisions.
·
Star Chamber Review of Directorate Proposals
Star Chambers are
common practice across business and local authorities and are
effectively a form of internal peer review. They can involve both
officers and members as desired. The intention is to utilise a Star
Chamber process later in the budget process when proposals are
reaching a more developed state to test each directorate’s
hypotheses and rationale for proposed savings, investments or cuts
and, in particular, understand and test delivery risks, assess the
capacity required to achieve change, understand impacts on
equalities, city partners or corporate priorities, review any
potential legal or financial risks, and, in particular, consider
any impacts on other council services. This process should also
look at associated capital programme requirements and any
cross-cutting or corporate proposals.
3.16 These processes
are in addition to the basic requirement for all services,
Directorate Management Teams (DMTs) and the Executive Leadership
Team (ELT) to explore all potential options for generating savings
within their directorates and on a cross-cutting, council-wide
basis.
2024/25 Budget Estimates
3.17 The table below
sets out the projected inflationary cost increases, demographic
(demand) pressures and commitments for 2024/25 developed on the
basis set out in paragraph 3.9 above.
Table: Projected Budget Position 2024/25
Cost and
Demographic Pressures
|
Estimate
|
|
£m
|
General Inflation
assumptions including 2024/25 Pay Award
|
10.392
|
Budget
Commitments (mainly capital financing)
|
5.581
|
Grant reductions
(New Homes Bonus/Services Grant)
|
0.669
|
Change in
contribution to reserves
|
2.454
|
2023/24 pay award
above 3.75% base provision
|
3.809
|
General Fund
energy contract inflation
|
0.500
|
PFI contract
inflation (Waste and Schools PFIs)
|
1.093
|
Children's
Social Care – provider and other cost increases
|
2.188
|
Demographic
pressures - Looked after children and Care Leavers
|
1.457
|
Adult
Social Care (including Learning Disability services) –
provider and other cost increases
|
8.532
|
Demographic
pressures - Adult Social Services including Learning
Disabilities
|
3.740
|
Temporary
Accommodation and Rough Sleepers – cost and demand
pressures
|
2.050
|
Home
to School Transport – cost and demand pressures
|
0.927
|
Housing
Benefit Subsidy shortfall
|
0.700
|
Income
and Commercial Rent pressures (due to falling demands)
|
2.020
|
All
other pressures across council services
|
2.799
|
Total Cost and
Demographic Pressures
|
48.911
|
|
|
Funding and
Taxation Resources
|
|
|
|
Social Care
additional funding (announced)
|
-5.390
|
Additional
government funding (assumption of £0.5 billion extra
nationally)
|
-2.500
|
Business rates
growth and appeals change (+1%)
|
-0.648
|
Business rates
change (+5.4% based on projected OBR Sept CPI)
|
-4.348
|
Revenue Support
Grant increase (+5.4% based on OBR Sept CPI)
|
-0.428
|
Council Tax
estimated tax base growth (+0.9%)
|
-1.630
|
Council Tax
increase (2.99% assumed)
|
-5.190
|
Adult Social Care
precept (2% assumed)
|
-3.471
|
Total
|
-23.605
|
|
|
Budget Gap
(Savings Requirement) 2024/25
|
25.306
|
3.18 The estimates and assumptions above, based on the
best information available, indicate that a substantial budget gap
of £25.306m would need to be addressed in order to balance
the budget. However, it must be remembered that all estimates at
this very early stage of the process, and in a volatile cost and
demand environment, are subject to change and will be reviewed and
updated throughout the budget process.
3.19 For planning purposes and recognising that it will
take many months to develop robust proposals and undertake all of
the processes outlined in paragraph 3.15 above, ELT and
DMTs will work on the basis of addressing the £25.306m
shortfall identified above. This will also include focusing on
managing costs and demands in the current year which can contribute
to improving trends together with working up savings, cost
reduction and demand management proposals for next year and the
following 3 years.
3.20 Excluding generic cost pressures such as pay awards,
energy costs and other commitments, the budget gap almost exactly
correlates to cost and demand pressures from services
(£25.506m). Therefore, managing these pressures is key to
resolving the council’s budget challenges.
Medium Term Financial Projections 2024/25
to 2027/28
·
Demographic pressures are based on
detailed estimates for 2024/25 and then moderated estimates for
2025/26 onward;
·
2.99% Council Tax increase in 2024/25 and
then reverting to 1.99% thereafter;
·
2.00% Adult Social Care precept 2024/25,
reverting to zero thereafter;
·
(Average) Pay awards of 3% in 2024/25 and
then 2.5% thereafter;
·
3% annual income target/generation
uplifts over the period;
·
Average 3.5% social care third party
provider payment increases for 2024/25 reducing to 3%, then 2.5%
thereafter;
·
Variable 1.00% to 3.50% cash limits on
non-pay budgets from 2024/25 onwards;
·
Business Rate uplifts to follow OBR CPI
inflation forecasts;
·
Council Tax taxbase growth ranging from
0.9% to 0.75% over the period;
Table: Indicative Medium Term Financial
Projections
Summary Projections and Budget Gaps
|
2024/25
|
2025/26
|
2026/27
|
2027/28
|
|
£m
|
£m
|
£m
|
£m
|
Commitments (from previous decisions)
|
7.123
|
4.026
|
0.988
|
0.589
|
Net Inflation (on Pay, Prices, Income, Pensions)
|
10.392
|
9.041
|
8.142
|
8.271
|
Subtotal
|
17.515
|
13.050
|
9.130
|
8.860
|
Net Investment in priority/demand-led services
|
26.006
|
13.050
|
11.050
|
11.050
|
New grant funding assumed
|
(2.500)
|
0.000
|
0.000
|
0.000
|
Projected Net Tax Base changes
|
(15.715)
|
(6.342)
|
(5.832)
|
(6.002)
|
Predicted Budget Gaps
|
25.306
|
19.775
|
14.348
|
13.908
|
3.22 The medium term projections could be affected by a
wide range of factors as follows:
·
Higher or lower demands and cost
pressures than projected;
·
Higher or lower tax base
movements;
·
Further movements in locally or
nationally negotiated pay;
·
Higher or lower inflation than
assumed;
·
More or less favourable government grant
settlements;
·
Potential changes to the ‘excessive
council tax’ capping rules and/or precepting or other more
fundamental changes to local government funding;
·
Changes in interest rates (impacting on
financing budgets); and
·
Actuarial changes to employers’ LG
pension contributions.
Many of these
can have significant impacts on medium term projections in either
direction. However, it is important to attempt to estimate future
costs and resources as this gives early indications of potential
future financial challenges and can inform decision-making now,
particularly with regard to setting in train longer term programmes
to address financial sustainability.
3.23 Based on the analysis above, options to address
budget gaps totalling £73.337m over the medium term period
2024/25 to 2027/28 will need to be developed.
3.24 One-off
resources may be needed in 2024/25 for a wide range of reasons
which could present additional financial challenges as these would
require identification of resources to meet any commitments.
One-off resources may be required to cover the following:
·
Any Collection Fund deficits **;
·
Any General Fund outturn overspend (i.e. TBM overspend) **;
·
Any increase to provisions or reserves required **;
·
Any delay or deferral to implementation of 2024/25 savings (to
manage so-called ‘part-year effects’ until the
full-year saving is achievable);
·
Any unavoidable one-off expenditure or commitments;
·
Any one-off allocations for priorities (subject to availability of
resources).
**
The reverse is also true whereby surpluses or underspends could
increase the availability of one-off resources or, at least, reduce
the call on one-off resources.
3.25 At this stage
there is likely to be a one-off resource requirement to continue
diseased tree management costing at least £0.500m and there
are also potential implementation and capital costs that could
arise from the Environment Act 2021 in relation to food and other
waste collection changes. The latter changes are also likely to
have significant ongoing revenue implications, including capital
financing. It is unclear when or if these requirements will be
placed on local authorities but the presumption at this stage is
that the doctrine of ‘New Burdens’ will apply and that
any additional funding requirements will be met by government
within the Local Government Financial Settlement.
4
CAPITAL STRATEGY AND CAPITAL INVESTMENT PROGRAMME
5 Year Capital
Investment Programme
4.1
The current Capital Strategy was approved by Budget Council in
February 2023 along with scheme-by-scheme capital programme
estimates that were incorporated into the council’s Budget
Book. The aim of the Capital Strategy is to ensure that all members
can understand and determine the overall long-term policy
objectives and resulting capital strategy requirements, governance
procedures and risk appetite of the council. The capital
expenditure estimates incorporate planned rolling investment
programmes alongside major infrastructure, housing and
sustainability schemes.
Rolling programmes
4.2
The majority of the council’s capital investment is within
rolling programmes. The key programmes are as follows:
·
Carbon Neutral investment programme.
·
Investment in new build housing through the Housing Revenue Account
and Housing Joint Venture (with Hyde Housing);
·
Investment in maintaining and improving the Council Housing Stock
through the Housing Revenue Account;
·
The Education Capital programme provides investment from central
government which includes New Pupil Places, Education Capital
Maintenance and Devolved Formula Capital for schools;
·
Disabled Facilities Grants;
·
The Local Transport Plan (LTP) covering a wide range of
transport-related schemes;
·
The Information Technology & Digital Investment Fund to
maintain and upgrade the council’s infrastructure and IT
architecture;
·
The Asset Management Fund (AMF) to maintain operational buildings,
improve sustainability and reduce long term maintenance costs;
·
Corporate Planned Maintenance (PMB) to undertake planned building
works and upgrades;
·
The Strategic Investment Fund (SIF) to provide project support for
major regeneration programmes that draw in substantial private
sector investment;
·
Vehicle and plant annual replacement programme.
4.3
The current strategy identifies longer term capital investment
plans as well as a funding strategy and the potential outcomes for
each investment plan. This strategy includes major investment
requirements such as investment in Kingsway to the Sea, partnership
investment through major projects such as Valley Gardens, New Homes
for Neighbourhoods, the Home Purchase scheme, the Housing Joint
Venture, Heritage Lottery Fund bids such as the Royal Pavilion
Estates Regeneration, and plans for investment into the seafront
infrastructure at Madeira Terrace.
4.4
Government funding through the City Deal has been received to
support the development of Longley Industrial Estate including the
refurbishment and expansion of New England House. Local Growth Fund
(LGF) grants have been approved from the Coast to Capital Local
Enterprise Partnership (C2CLEP) to support the Black Rock Enabling
project, Valley Gardens Phase 3 and the Brighton Research
Innovation Fibre Ring projects. The Kingsway to the Sea project has
received significant funding through the Government’s
Levelling Up Fund. Longer term investment for coast protection is
also incorporated into the 5-year strategy which includes
government match-funding from the Environment Agency.
4.5
Capital receipts from the sale of surplus land and buildings
support the capital programme and the projections are regularly
reviewed having considered the social value implications of any
decision to dispose first. The council’s existing strategy is
to re-balance the property portfolio by disposing of low or
non-performing commercial properties and reinvesting in more viable
property investments. This ensures costs can be minimised and
rental growth optimised to ensure best value is achieved. However,
this is now considerably more challenging as borrowing from the
Public Works Loan Board is now prohibited for commercial property
investment and so the current focus is on investment in existing
assets.
4.6
Capital receipts are under severe pressure due to competing demands
for the resources and the certainty and speed with which capital
receipts can be realised. This puts in jeopardy the council’s
ability to support the following objectives:
·
Funding of annual investment funds such as the Strategic Investment
Fund (SIF) and Asset Management Fund (AMF) referred to above;
·
Re-balancing of the commercial property portfolio;
·
Support for accelerating housing supply schemes; and
·
Funding of the Modernisation Fund which supports implementation of
savings and improvement programmes (see below).
Review of the
Existing Capital Programme and Future Requirements
4.7
The Capital programme, agreed at Budget Council in February 2023
included £211.7m investment plans for 2023/24. This included
a large number of schemes reprofiled from 2022/23 and in some cases
previous years. Since the programme was set, a further £25m
of reprofiling and slippage in 2022/23 was approved by this
committee in June 2023.
4.9
In recent years there has been a significant increase in the number
of schemes funded through borrowing. At the time decisions were
made borrowing rates were very low, however, the recent rapid
increase in the Bank of England Base Rate means that borrowing
costs are at their highest in 15 years. Therefore, continuing with
delayed schemes puts increased pressure on the council’s
financing costs budget. In addition, the diminishing availability
of capital receipts over the last 3 years has resulted in borrowing
being more frequently used as an alternative source of financing.
Delivery of the capital programme also has a direct impact on the
council’s cashflow forecasting; the greater the certainty of
cashflow, the greater the opportunities for better investment
returns on cash held.
4.10 As noted in
paragraph 3.15 above, a key part of the budget process and in-year
budget management will be a review of the capital programme and its affordability and
deliverability. This should include recommendations for
rationalising and prioritising schemes to ensure approved projects
are deliverable and affordable and to ensure that capital
investment is aligned to Corporate Plan priorities and supports the
council’s medium term financial sustainability.
Modernisation &
Enabling Investment
4.12 The
Modernisation fund has been resourced through the flexible use of
capital receipts. This is where the government allows councils to
fund revenue expenditure from capital receipts provided the
expenditure supports improved value for money and/or the future
realisation of revenue savings. This flexibility expires in March
2025. Irrespective of the expiry, the council has a shortfall of
capital receipts at present to fund this programme and therefore,
for the continued use of this flexibility, disposals of assets will
need to be progressed at pace. In 2023/24, the expected requirement
on the current Modernisation Fund is as shown in the table below
and indicative requirements are given for 2024/25.
Modernisation investment for later
years of the Medium-Term Financial Strategy will need to informed
by the 2024/25 budget process but will also need to be managed in a
different way due to the ending of capital receipt flexibilities
and the limited availability of revenue resources. Future
modernisation business cases are therefore likely to need to become
self-financing and generate a return on investment within a
reasonable timeframe (2 to 5 years) to enable them to be
undertaken. The investment can be funded by reserves (subject to
availability) or netted off from savings proposals. The latter,
however, reduces the contribution that savings make toward closing
down budget gaps identified in the MTFS.
Table:
Modernisation and Enabling Investment
Programme
Area
|
2023/24
|
2024/25
|
£m
|
£m
|
Invest to Save
(4-Year Plans)
|
0.350
|
0.000*
|
Customer
Digital
|
1.750
|
1.750
|
Modernisation
enablers
|
0.940
|
1.040
|
Managing staffing
changes
|
0.400
|
0.300
|
Total
|
3.440
|
3.090
|
Funded
by
|
|
|
Flexible use of
capital receipts
|
3.240**
|
1.890**
|
Converted to
mainstream funding
|
0.200
|
1.200
|
To be
identified
|
0.000
|
0.000
|
Total
|
3.440
|
3.090
|
* Invest to save
projects will need to become self-financing
** Subject to new capital
receipts being realised before March 2025
The current
elements of the Modernisation Fund are as follows:
4.13 Customer Digital: The council’s Digital programme initially
concentrated on developing the digital infrastructure and providing
the web design and content management applications and tools
necessary to develop digital services. In the last 3 years there
has been development of a significant number of digital services
and portals, particularly driven by the pandemic where digital
access became critical to ensure accessibility and continuity of
service. Digital forms, apps and services can enable enhanced data
management and a better customer experience, however, supporting
and continuing to mature the council’s digital environment
requires significant ongoing investment that ultimately should be
mainstreamed within the annual revenue budget.
4.14 Modernisation Enablers:This investment covers project teams and staffing
necessary to support service directorates in the delivery of large
savings and improvement programmes. This includes Project &
Programme Managers (PMO), Business Improvement analysts and
‘Workstyles’ project staff, as well as investment in
the People Promise, internal communications and change management.
This resource has become more critical over time as management and
administrative savings have reduced services’ staffing
capacity to support improvement programmes directly. This resource
should also be mainstreamed within the annual revenue budget if
possible as councils now operate in an environment of permanent
change driven by both national and local policy and ongoing
financial challenges.
4.15 Invest-to-Save (4-Year Plans):
These investments cover direct investment
by services to enable them to achieve planned savings and
improvements. This can include commissioning expert advice or
professional services, providing temporary additional capacity, or
investing in equipment, IT, training & development and systems
developments to support service changes. Investments must be
supported by Business Cases which are considered and scrutinised by
the Corporate Modernisation Delivery Board (CMDB) chaired by the
Chief Executive. The use of the resources is focused on helping
services modernise and achieve cost reductions and efficiencies as
a further aid to achieving financial sustainability. As noted
earlier, the limited availability of capital receipts and the
ending of ‘flexibilities’ means that business cases
will need to become self-financing in future i.e. generate a return
on investment within a reasonable time period.
4.16 Managing Staffing Changes: Many savings measures will involve service redesign
or modernisation (e.g. becoming more digital) that may have an
impact on staffing requirements. This is normal within local
authorities as they strive to improve value for money as part of
their Best Value duty under the Local Government Act 1999 and as
part of their budget strategies. Managing change often
involves potential redundancy or supporting redeployment as a way
of managing the process and this requires funding to meet potential
severance costs and potential pension strain costs. The
council’s rules for good business practice require that
severance costs should normally be repayable from associated
staffing savings within 2 years.
4.17 The Modernisation Fund is currently managed by the
Corporate Modernisation Delivery Board (CMDB) chaired by the Chief
Executive and including Executive Directors and the CFO. Decisions
regarding the detailed use of the Modernisation Fund are governed
by Financial Regulations, and Committee and Officer delegations as
set out in the Council’s constitution. Larger investment
decisions, above £0.500m are therefore reported to committee
as a matter of course as these are above officer delegations.
Decisions leading to investment in capital assets are also reported
to committee as per Financial Regulations, either as a separate
report or through the capital appendices of Targeted Budget
Management (TBM) monitoring reports.
4.18
The capital plan for the HRA is
split into two main areas in investment, this being improving the
quality, safety, and energy efficiency of council homes and in new
housing supply. Investment in existing stock is funded from direct
revenue funding from tenants’ rents (including associated
rent rebates) and HRA borrowing that is supported by tenants’
rents over a longer period. Whilst investment in new supply is
mainly funded from retained capital receipts (including Right to
Buy sales and commuted sums), grant funding and HRA
borrowing.
4.19
The HRA capital investment
programme for 2023/24 to 2027/28 is informed by the most recent
stock condition review and survey as well as the existing and
emerging priorities of the HRA Asset Management Strategy which is
currently under review. Key considerations include improving the
quality of homes and working in consultation with tenants and
leaseholders to agree planned and major works programmes. Another
emerging key priority relates to the investment required in Health
& Safety requirements in anticipation of forthcoming
legislative and regulatory changes impacting social housing
landlords following the Grenfell Tower tragedy. Investment also
continues in carbon reduction initiatives to support the
city’s commitment of becoming carbon neutral by
2030.
4.20
The HRA continues to look at
the range of initiatives it has to deliver additional housing and
meet the commitment to deliver new affordable council homes. These
initiatives include the New Homes for Neighbourhoods Programme,
Home Purchase Scheme, Converting Spaces programmes and the Homes
for the City of Brighton & Hove Joint Venture.
4.21 Work will continue through 2023/24 to
deliver housing supply pipeline schemes. The Home Purchase Scheme
will continue to explore opportunities to buy back ex-right-to-buy
properties, whilst the extended Home Purchase Scheme will look at
off the shelf purchase opportunities to increase the supply of
affordable housing within the HRA.
5
TIMETABLE
5.1
The indicative timetable for developing
and approving the 2024/25 budget and MTFS is given below. The
timetable is in outline only and does not include all aspects of
member involvement or wider consultation that will normally need to
be undertaken with staff, unions, partners, service users and
residents.
Table: Outline General Fund Budget Planning
Timetable
Date
|
Who
|
What
|
13
July 2023
|
SFCR
Committee
|
TBM
Month 2 Forecast 2023/24
General
Fund Budget Planning & Resource Update 2024/25
|
July
– Oct
|
ELT
|
Develops
Medium Term service and financial plans including the workstreams
set out in this report (para 3.15)
and budget proposals to address budget gaps for 2024/25 to
2027/28
|
5
Oct 2023
|
SFCR
Committee
|
TBM
month 5 (August)
|
Oct/Nov
|
Government
|
Possible
Autumn Statement announcement
|
7
Dec 2023
|
SFCR
Committee
|
TBM
month 7 (October)
Council
Tax Reduction Scheme Review 2024/25
|
December
|
Government
|
Provisional
Local Government Finance Settlement 2024/25
|
25
Jan 2024
|
SFCR
Committee
|
Council
Tax and Business Rates Tax Base report
|
February
|
Government
|
Final
Local Government Financial Settlement 2024/25
|
8
Feb 2024
|
SFCR
Committee
|
2024/25
General Fund and HRA Revenue & Capital Budget reports including
the Capital and Treasury Management strategies.
TBM
month 9 (December).
|
22
Feb 2024
|
Budget
Council
|
Approval
of the 2024/25 General Fund and HRA Revenue & Capital Budget
including the Capital and Treasury Management
strategies.
|
6
ANALYSIS & CONSIDERATION OF ANY ALTERNATIVE OPTIONS
6.1
The budget process allows all parties to
engage in the examination of budget proposals and put forward
viable alternative budget and council tax proposals, including
amendments, to Budget Council on 22 February 2024. Budget Council
has the opportunity to debate the proposals put forward by the
Strategy, Finance & City Regeneration Committee at the same
time as any viable alternative proposals.
7
COMMUNITY ENGAGEMENT AND
CONSULTATION
7.1
No specific consultation has been
undertaken in relation to this report. However, the development of
the council’s budget is a major undertaking and proposals can
affect a wide range of services. Consultation and engagement will
need to be undertaken with staff, unions, partners, service users,
residents and the community and voluntary sector as appropriate.
Proposals for consultation and engagement will be developed with
the Administration for the Autumn/Winter period in advance of
proposals coming forward in February for full Council approval.
This report will also be shared widely as it signals to all
stakeholders the anticipated financial challenge facing the council
for next year and beyond.
8
CONCLUSION
8.1
The council is under a statutory duty to
set its budget and council tax before 11 March each year. This
report sets out information on projected costs, investments and
resources for 2024/25 to 2027/28. It also provides an outline
timetable for considering options to develop the 2024/25 annual
budget and MTFS.
9
Financial Implications:
9.1
These are contained in the body and
appendices of the report.
Finance
Officer Consulted: James Hengeveld Date:
3/7/23
10
Legal Implications:
10.1 The process of
formulating a plan or strategy for the council’s revenue and
capital budgets falls within the Scheme of Delegation for Strategy,
Finance & City Regeneration Committee.
10.2
This report complies with the
Council’s process for developing the budget framework, in
accordance with the Council’s Budget and Policy Framework
Procedure Rules as set out in Part 7.2 of the
Constitution.
Lawyer Consulted: Elizabeth
Culbert Date:
03/07/23
11
Equalities Implications:
11.1 For any significant budget changes proposed in
2024/25, it is proposed to use the council’s well-established
screening process to develop Equality Impact Assessments (EIAs).
Key stakeholders and groups will be engaged in developing EIAs but
it will also be important to consider how members, partners, staff
and unions can be kept informed of EIA development and the
screening process. In addition, where possible and proportionate to
the decision being taken, there may be a need to assess the
cumulative impact of the council’s decision-making on
individuals and groups affected in the light of funding pressures
across the public and/or third sectors. The process will ensure
that consideration is given to the economic impact of
proposals.
12
Sustainability Implications
12.1 The council’s revenue and capital budgets will
be developed with sustainability as a key consideration to ensure
that, wherever possible, proposals can contribute to reducing
environmental impacts and support progress toward a carbon-neutral
city.
13
Other Implications
Risk and Opportunity Management
Implications:
13.1 There are a range of risks relating to the
council’s short and medium term budget strategy including the
ongoing economic impact of the higher inflationary environment, the
impact of the cost of living crisis, further potential reductions
in grant funding, the impact of legislative changes, and/or other
changes in demands. The budget process will normally include
recognition of these risks and identify potential options for their
mitigation. In the current volatile financial climate, the level of
risk that the council may be prepared to carry is likely to be
higher than in normal circumstances. An indication of potential
risks and sensitivities is given in Appendix 3 of the
report.
SUPPORTING DOCUMENTATION
Appendices:
1.
Medium
Term Financial Assumptions and Projections
2.
Resources
Update
3.
MTFS
Risks and Sensitivities